10 Implementation

The total cost to implement this recovery plan is estimated to be $81,500 over five years. This amount does not include site management costs, as these are yet to be determined. A total of $59,000 will be provided as in-kind contributions with an additional $22,500 required to implement actions that are currently unfunded. Additional funds will be sought from sources including the Natural Heritage Trust, Environmental Trust, industry sponsors, the NSW State Biodiversity Program, Threatened Species Network, Threatened Species Appeal and from the DECs annual operational provisions for threatened species programs.

Table 7 details the costs and identifies the parties responsible for the implementation of specific recovery actions.