Supervising Scientist Division

Supervising Scientist Annual Report 2002 - 2003

Supervising Scientist, Darwin, 2003
ISBN 0 642 24383 2
ISSN 0 158-4030

2 - Environmental assessments of uranium mines (continued)

2.2 Ranger (continued)

2.2.4 Investigation of Alleged Deficiencies in Environmental Management at Ranger

As reported in the Supervising Scientist's Annual report 2001-02, on 5 April 2002, a former employee of ERA at Ranger uranium mine's environmental laboratory, wrote to the Commonwealth Minister for the Environment and Heritage, the Northern Territory Minister for Resource Development and a number of Commonwealth and Northern Territory officials. In his letter and attached report, concerns were expressed about a number of issues relating to environmental management and reporting by ERA at the Ranger mine between 1996 and 1998.

At the request of the above Ministers, an investigation of the issues raised by Mr Kyle was carried out and a report was submitted to Ministers in September 2002. It has since been published as Supervising Scientist Report 171.

The report covered the following issues raised in the former employee's submission:

Tailings Spill in Corridor Road

In December 1997, a tailings spill occurred at Ranger. With respect to this incident, it was alleged that ERA under-reported and misreported the extent of the spillage outside the Restricted Release Zone (RRZ), failed to clean up in a timely manner the spilled tailings material within the RRZ, and, by its inaction, probably caused an increase in uranium in Retention Pond 2 (RP2).

The investigation concluded that:

Discharge of water from the Restricted Release Zone into a tributary of Gulungul Creek

It was alleged that ERA routinely discharged from the RRZ water containing high concentrations of uranium from the southern external walls of the tailings dam into the headwaters of Gulungul Creek, that the ERA Laboratory Manager refused permission for an investigation of the effects of this discharge, and that he instructed the former employee not to record a higher than normal result for uranium in Gulungul Creek waters. It was claimed that this result was obtained from two separate samples, each of which was analysed in triplicate.

The investigation concluded that:

Procedures in ERA's Environmental Laboratory

A number of issues related to the performance of ERA's chemical analysis laboratory were also raised. Specifically, it was claimed that laboratory management consistently refused to address technical issues that compromised the performance of the laboratory, that this led to an inability to honour the conditions of its licence to operate the mine, and that ERA did not rectify problems even when it was demonstrated that the problems were valid.

The investigation of these laboratory related issues was, to some extent, superficial in that it relied heavily upon the assessment of ERA's performance in these areas by the appropriate authority, the National Association of Testing Authorities (NATA).

The investigation concluded that:

Overall Conclusion and Recommendations

The overall conclusion of the investigation was that, apart from the previously reported breach of the Ranger Authorisation arising from the spillage of tailings outside the Restricted Release Zone on 19 December 1997, no evidence was found that ERA had operated otherwise than in accordance with its Authorisation and the Commonwealth's Environmental Requirements.

The report recommended that the Ranger Minesite Technical Committee:

  1. Should, in its current review of the Ranger monitoring programme, assess the need for load estimation in the chemical monitoring of the Ranger mine, taking into account existing biological monitoring programmes.
  2. Should consider, within the context of Best Practicable Technology, whether or not uncontrolled discharges of water from the region south of the tailings dam to the Gulungul Creek system should continue.
Implementation

The recommendations of the report were fully implemented. The MTC considered the need for load estimation in its review of the Ranger monitoring programme. It concluded that load estimation was not required in order to draw sound conclusions regarding the extent to which the environment was protected from the potential impacts of mine derived contaminants in waters. The biological monitoring programme, which integrates the effects of all stressors, provides the best data from which to make such assessments. However, load estimation was considered to be useful in the context of understanding the behaviour of the Ranger Water Management System, and in optimising that system.

As a precautionary measure, ERA pumped water from the region south of the tailings dam back to the tailings dam during the 2002-03 wet season whilst the MTC considered whether uncontrolled discharges from this area should be permitted. The conclusion reached by the MTC was that uncontrolled discharges from this area posed a negligible risk to the environment, and as such, would be permitted.