Energy efficiency

Reference manual

  1. Introduction: setting the scene 
  2. Selecting the best motor and equipment 
  3. Commissioning 
  4. Motor and system maintenance and operation 
  5. Motor repair and replacement 
  6. Utility management  
  7. Maintenance management systems: plant inventory and records 

Commissioning

Commissioning takes place after:

Failure to pay attention to detail when commissioning electric motors and motor driven equipment can lead to a dramatic increase in operating costs, through inefficient operation, and an increased risk of early motor or equipment failure.

This section outlines basic steps of best practice commissioning and provides an easy-to-use checklist. It also explains some of the major consequences of poor commissioning practices.

The benefits of best practice commissioning

A best practice approach to commissioning electric motors and driven equipment will:

Steps to best practice commissioning

To achieve best practice commissioning you must develop a plan to allow the technicians involved adequate time to thoroughly complete the tasks. Your best practice commissioning plan should include:

  1. A requirement that all your organisation's safety procedures are followed.
  2. Clear delegation of authority and responsibility.
  3. A method for checking that the specifications of the supplied equipment are in line with the process design requirements and that the equipment documentation is complete (including installation requirements, operation guidelines and maintenance specifications).
  4. A method for checking that the equipment is set up correctly, mechanically and electrically, in accordance with the original manufacturer's specifications. See checklist below.
  5. Verification that the actual machine output meets design intent at the specified load range. It is important that the machine delivers what is required and not any excess, which becomes waste.
  6. Refinement of the control system to optimise energy efficiency and reliability for typical operation.
  7. A process for recording and documenting the results of commissioning for future reference and updating relevant maintenance profiles and schedules.
  8. Ensuring relevant reference manuals are available to operation and maintenance staff.
  9. Ensuring that appropriate staff know or are trained in the skills necessary to operate and maintain the equipment.

Often all commissioning tasks cannot be completed before the machine is required. It is important to have a system in place which ensures that unfinished tasks are completed at the earliest opportunity and not forgotten.

Commissioning checklist

Your best practice motor commissioning plan must be supported by a commissioning checklist. The basic checklist below covers the key actions required when commissioning new motors. You should also complete any tasks or other checklists provided with the equipment. If you have done this and can tick all the boxes below, your equipment should deliver reliable and economic service. It is also important during commissioning that you follow all of your organisation's relevant safety procedures.

Consequences of poor commissioning

The failure to apply an appropriate commissioning strategy for your electric motors and driven equipment can lead to the following consequences:

Case study

Poor commissioning reduces reliability and efficiency

A 300 kW motor operating in a paper processing plant on continuous duty is effected by 'soft foot', a condition caused by uneven shimming of the stator feet to foundation. The first effect of the condition is impedance asymmetry. This leads to increased thermal rise, increased power consumption, increased running costs and the risk of reduced machine life.

In this case, the protection on the machine did not flag a problem because the machine was oversized for the application. Protection was set to the motor's nameplate (300 kW) rather than the motor's actual peak load (245 kW). The differential between real load and protection setting was topped up with undetected losses.

Parameter With soft-foot Without soft-foot Difference

Impedance imbalance
Heat rise
Current
Power load
Operating cost (p.a.)

12.96%
81C
85A
287.82 kW
$84 620.12
0.86%
53C
72A
245.07 kW
$72 049.26
12.1%
28C
13A
42.76 kW
$12 570.86